Download page Use Case: Validation on Period Start Date and Period End Date.
Use Case: Validation on Period Start Date and Period End Date
This use case explains how Conga Billing validates Period Start Date and Period End Date on theDefine invoice date and amountpage while creating a billing plan.
Go to your quote page, go to the Billing Plan related list, and click New Billing Plan. TheSelect Line Item(s)page is displayed.
Select the following products for which the billing plan must be created.
Line Item
Start Date
End Date
LI-001
1-Mar-22
30-Nov-22
LI-002
15-May-22
30-Nov-22
Click Next. TheDefine Billing Planpage is displayed.
From the Plan Typedrop-down, select Fixed.
Leave the Billing Start Date and Billing End Date fields blank, and click Next.
If you do not select the dates, Billing will auto-calculate the Start Date and End Date from the selected line items.
On the Number of Installments field, enter 3. TheDefine invoice date and amountpage is displayed.
Plan Item Name
Period Start Date
Period End Date
Ready for Invoice Date
Payment Term
Installment 1
1-Mar-22
Installment 2
Installment 3
When thepage is loaded, this field is blank.
30-Nov-22
Conga Billing populates Period Start Date and Period End Dateby default, based on the following logic:
Period Start Date of the first instalment = MIN (Billing Start Date of all lines on the billing plan). You can overwrite it with a different date, but it must be greater the default date and less than the Period End Date.
Period End Date of the last instalment = MAX (Billing End Date of all lines on the billing plan). You can overwrite it with a different date, but it must be less than the default date and greater than the Period Start Date.
Overwrite the dates based on the following guidance.
Plan Item Name
Period Start Date
Period End Date
Ready for Invoice Date
Payment Term
Installment 1
15-Apr-22
It is defaulted as 1-Mar-22. You can overwrite with a date >= 1-Mar-22 but it must be <= Period End Date (30-Nov-22).
Installment 2
Installment 3
30-Oct-22
It is defaulted as 30-Nov-22. You can overwrite with a date >= Period Start Date (1-Mar-22) but it must be <= 30-Nov-22.
When you select Period Start Date and Period End Date for the installments, Conga Billing validates that the dates are in the allowable range. Billing displays error messages if you select a date outside these period ranges.