Editing Installments on an Existing Milestone Billing Plan
You can edit the following fields on the billing plan:
Selection | Editable Fields | Non-editable Fields |
---|---|---|
Select Line Item(s) | None | NA |
Define Billing Plan |
|
|
Define invoice date and amount |
| The installments whose status is other than Expected The Percent/Amount on the last installment. |
If only the amount is changed, then new billing schedules with the changed amount are created in Pending Milestone status, and the existing ones in Pending Milestone statuses are superseded.
You created a milestone-based plan. Assuming that the amount payable is USD 1,2000.00 and the milestone dates are 01-August-2025, 15-September-2025, 10-October-2025, three billing schedules are generated in Pending Milestone status.
As part of editing the installments, you changed the amount to USD 5,000.00 and updated the Actual Date to 05-August-2025 for the first installment. New billing schedules are created to reflect the changed data, and the existing ones are superseded as follows:
Schedule ID | Period Start Date | Period End Date | Fee Amount | Status |
---|---|---|---|---|
BS-1 | 01-August-2025 | 01-August-2025 | USD 4000.00 | Superseded |
BS-2 | 15-September-2025 | 15-September-2025 | USD 4000.00 | Superseded |
BS-3 | 10-October-2025 | 10-October-2025 | USD 4000.00 | Superseded |
BS-4 | 05-August-2025 | 05-August-2025 | USD 5000.00 | Superseded |
BS-5 | 05-August-2025 | 05-August-2025 | USD 5000.00 | Pending Billing |
BS-6 | 15-September-2025 | 15-September-2025 | USD 3,500.00 | Pending Milestone |
BS-7 | 10-October-2025 | 10-October-2025 | USD 3,500.00 | Pending Milestone |